BHS AND REDS INSTALLATION MANUAL
34
4
4.6 FINAL CHECKS
After sending the correct parameter configuration, the SC6000 will restart and the system is
ready to work.
Verify the following:
make sure that for each scanner an asterisk (“*”) is shown on the SC6000’s status
window
make sure that the speed shown by the SC6000 is consistent with the conveyor speed
run parcels with a known label so that it is read only by scanners on one side. Use the
Last Code & Read Maskwindow to check that the data output matches the expected
results
make sure that the Good Read rate (shown in the “Statistics Window”) is high
perform a system Backup so it will be possible to replace scanners or controller in case of
a failure, see par. 5.1 for details.
4.7 COMMISSIONING
During commissioning the whole system is tested to verify if it functions according to the
specifications. Please refer to the Commissioning Check List given in Appendix B.